The right-of-way acquisition process will begin in the final phase of design. A right-of-way agent will notify and individually work with each impacted property owner to obtain necessary right-of-way and/or easements.

Construction is planned for spring 2024 through fall 2025.

 

All dates are subject to change.

 
  • Surveys and studies

    Fall 2020-spring 2022
  • First open house

    Oct. 8-24, 2021
  • Preliminary design

    summer 2021-summer 2022
  • Second open house

    Oct. 28-Nov. 13, 2022

    You are here

  • Final design

    Fall 2022-summer 2023
  • Right-of-way acquisition process

    Winter 2022/23-Winter 2023/24
  • Contractor bids

    Winter 2023/24
  • Construction

    Summer 2024-fall 2025
  • West culvert replacement

    Summer 2024
  • East culvert replacement

    Summer 2025